Item List 255395 |
Date:02/06/2026 |
|
|
RTF Report: CATITEM |
KENTUCKY TRANSPORTATION CABINET
| Contract ID | 255395 | Primary Project Number | BR07802892500 |
| Contract Description | KY 289 | ||
| Primary County | MARION | Fed/St Number | STP BRZ 9030 (513) |
| Vendor ID | 00138 | Vendor Name | HAYDON BRIDGE COMPANY INC |
| Bid Amount | $ 3,549,706.35 | ||
| SM- Project | BR07802892500 |
| Fed/State Number | STP BRZ 9030 (513) |
| Project Description | KY 289 |
| *********** |
| SM- Project | BR07802892500 | CATEGORY NUMBER | 0001 | CATEGORY Description | PAVING |
| PROJ LN # | Item Description | BID CODE | Bid Qty | Plan Qty | Unit Price | Unit | % of Bid Amt |
| 0005 | DGA BASE | 00001 | 2,434.000 |
2,434.000 |
$41.000 |
TON | 2.8 |
| 0010 | ASPHALT SEAL AGGREGATE | 00100 | 16.000 |
16.000 |
$215.770 |
TON | 0.1 |
| 0015 | ASPHALT SEAL COAT | 00103 | 2.000 |
2.000 |
$2,079.350 |
TON | 0.1 |
| 0020 | CL2 ASPH BASE 1.00D PG64-22 | 00212 | 1,245.000 |
1,245.000 |
$115.000 |
TON | 4.0 |
| 0025 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | 194.000 |
194.000 |
$150.000 |
TON | 0.8 |
| 0030 | ASPHALT MATERIAL FOR TACK | 00356 | 4.000 |
4.000 |
$685.190 |
TON | 0.1 |
Category Total $282,420.78 |
| SM- Project | BR07802892500 | CATEGORY NUMBER | 0002 | CATEGORY Description | ROADWAY |
| PROJ LN # | Item Description | BID CODE | Bid Qty | Plan Qty | Unit Price | Unit | % of Bid Amt |
| 0035 | ENTRANCE PIPE-15 IN | 00440 | 58.000 |
58.000 |
$85.000 |
LF | 0.1 |
| 0040 | ENTRANCE PIPE-18 IN | 00441 | 96.000 |
96.000 |
$90.000 |
LF | 0.2 |
| 0045 | REMOVE PIPE | 01310 | 102.000 |
102.000 |
$15.000 |
LF | 0.0 |
| 0050 | SLOPED BOX OUTLET TYPE 1-18 IN | 01433 | 2.000 |
2.000 |
$3,300.000 |
EACH | 0.2 |
| 0055 | DELINEATOR FOR GUARDRAIL BI DIRECTIONAL WHITE | 01987 | 10.000 |
10.000 |
$16.350 |
EACH | 0.0 |
| 0060 | BARRICADE-TYPE III | 02014 | 8.000 |
8.000 |
$225.000 |
EACH | 0.1 |
| 0065 | REMOVE PAVEMENT | 02091 | 404.000 |
404.000 |
$10.750 |
SQYD | 0.1 |
| 0070 | ROADWAY EXCAVATION | 02200 | 19,033.000 |
19,033.000 |
$18.500 |
CUYD | 9.9 |
| 0075 | GRANULAR EMBANKMENT | 02223 | 4,331.000 |
4,331.000 |
$57.000 |
CUYD | 7.0 |
| 0080 | REMOVE FENCE | 02265 | 284.000 |
284.000 |
$9.210 |
LF | 0.1 |
| 0085 | GUARDRAIL-STEEL W BEAM-S FACE | 02351 | 737.500 |
737.500 |
$32.870 |
LF | 0.7 |
| 0090 | GUARDRAIL TERMINAL SECTION NO 1 | 02360 | 3.000 |
3.000 |
$82.120 |
EACH | 0.0 |
| 0095 | GUARDRAIL END TREATMENT TYPE 1 | 02367 | 1.000 |
1.000 |
$3,551.470 |
EACH | 0.1 |
| 0100 | REMOVE GUARDRAIL | 02381 | 294.000 |
294.000 |
$4.140 |
LF | 0.0 |
| 0105 | RIGHT-OF-WAY MONUMENT TYPE 1 | 02429 | 15.000 |
15.000 |
$191.260 |
EACH | 0.1 |
| 0110 | WITNESS POST | 02432 | 15.000 |
15.000 |
$161.460 |
EACH | 0.1 |
| 0115 | CHANNEL LINING CLASS II | 02483 | 1,537.000 |
1,537.000 |
$44.500 |
TON | 1.9 |
| 0120 | CLEARING AND GRUBBING Area ~4 acres | 02545 | 1.000 |
1.000 |
$75,000.000 |
LS | 2.1 |
| 0125 | TEMPORARY SIGNS | 02562 | 216.000 |
216.000 |
$14.000 |
SQFT | 0.1 |
| 0130 | EDGE KEY | 02585 | 42.000 |
42.000 |
$115.000 |
LF | 0.1 |
| 0135 | FABRIC-GEOTEXTILE CLASS 1 | 02602 | 2,458.000 |
2,458.000 |
$3.200 |
SQYD | 0.2 |
| 0140 | FABRIC-GEOTEXTILE CLASS 2 | 02603 | 2,500.000 |
2,500.000 |
$2.250 |
SQYD | 0.2 |
| 0145 | MAINTAIN & CONTROL TRAFFIC | 02650 | 1.000 |
1.000 |
$30,000.000 |
LS | 0.8 |
| 0150 | PORTABLE CHANGEABLE MESSAGE SIGN | 02671 | 2.000 |
2.000 |
$1,250.000 |
EACH | 0.1 |
| 0155 | STAKING | 02726 | 1.000 |
1.000 |
$15,000.000 |
LS | 0.4 |
| 0160 | REMOVE STRUCTURE | 02731 | 1.000 |
1.000 |
$95,000.000 |
LS | 2.7 |
| 0165 | EROSION CONTROL BLANKET | 05950 | 122.000 |
122.000 |
$3.310 |
SQYD | 0.0 |
| 0170 | SBM ALUM SHEET SIGNS .125 IN | 06407 | 38.500 |
38.500 |
$53.400 |
SQFT | 0.1 |
| 0175 | STEEL POST TYPE 1 | 06410 | 48.000 |
48.000 |
$35.600 |
LF | 0.0 |
| 0180 | PAVE STRIPING-PERM PAINT-6 IN | 06515 | 3,036.000 |
3,036.000 |
$0.850 |
LF | 0.1 |
| 0185 | PAVE STRIPING-DUR TY 1-6 IN W | 06556 | 486.000 |
486.000 |
$13.000 |
LF | 0.2 |
| 0190 | PAVE STRIPING-DUR TY 1-6 IN Y | 06557 | 486.000 |
486.000 |
$13.000 |
LF | 0.2 |
| 0195 | REMOVE SIGN | 21373ND | 2.000 |
2.000 |
$47.620 |
EACH | 0.0 |
| 0200 | EROSION CONTROL | 21415ND | 1.000 |
1.000 |
$10,000.000 |
LS | 0.3 |
| 0205 | BARCODE SIGN INVENTORY | 24631EC | 6.000 |
6.000 |
$47.620 |
EACH | 0.0 |
| 0210 | THRIE BEAM GUARDRAIL TRANSITION TL-3 | 25078ED | 4.000 |
4.000 |
$3,170.680 |
EACH | 0.4 |
| 0215 | HISTORIC BRONZE PLAQUE | 26266EC | 1.000 |
1.000 |
$2,500.000 |
EACH | 0.1 |
| 0220 | INSTALL HISTORIC BRONZE PLAQUE | 26267EC | 1.000 |
1.000 |
$1,250.000 |
EACH | 0.0 |
Category Total $1,017,586.95 |
| SM- Project | BR07802892500 | CATEGORY NUMBER | 0003 | CATEGORY Description | BRIDGE |
| PROJ LN # | Item Description | BID CODE | Bid Qty | Plan Qty | Unit Price | Unit | % of Bid Amt |
| 0225 | STRUCTURE GRANULAR BACKFILL | 02231 | 184.000 |
184.000 |
$75.000 |
CUYD | 0.4 |
| 0230 | ARMORED EDGE FOR CONCRETE | 03299 | 48.000 |
48.000 |
$125.000 |
LF | 0.2 |
| 0235 | FOUNDATION PREPARATION | 08003 | 1.000 |
1.000 |
$165,000.000 |
LS | 4.6 |
| 0240 | CYCLOPEAN STONE RIP RAP | 08019 | 1,860.000 |
1,860.000 |
$80.000 |
TON | 4.2 |
| 0245 | TEST PILES | 08033 | 55.000 |
55.000 |
$350.000 |
LF | 0.5 |
| 0250 | PRE-DRILLING FOR PILES | 08039 | 50.000 |
50.000 |
$365.000 |
LF | 0.5 |
| 0255 | PILES-STEEL HP14X89 | 08051 | 216.000 |
216.000 |
$150.000 |
LF | 0.9 |
| 0260 | PILE POINTS-14 IN | 08095 | 12.000 |
12.000 |
$260.000 |
EACH | 0.1 |
| 0265 | CONCRETE-CLASS A | 08100 | 155.000 |
155.000 |
$1,350.000 |
CUYD | 5.9 |
| 0270 | CONCRETE-CLASS AA | 08104 | 237.000 |
237.000 |
$1,350.000 |
CUYD | 9.0 |
| 0275 | STEEL REINFORCEMENT | 08150 | 18,503.000 |
18,503.000 |
$2.820 |
LB | 1.5 |
| 0280 | STEEL REINFORCEMENT-EPOXY COATED | 08151 | 58,795.000 |
58,795.000 |
$2.070 |
LB | 3.4 |
| 0285 | DRILLED SHAFT 54 IN-SOLID ROCK | 20743ED | 48.000 |
48.000 |
$3,250.000 |
LF | 4.4 |
| 0290 | DRILLED SHAFT 60 IN-COMMON | 20744ED | 22.000 |
22.000 |
$3,250.000 |
LF | 2.0 |
| 0295 | ROCK SOUNDINGS | 20745ED | 20.000 |
20.000 |
$150.000 |
LF | 0.1 |
| 0300 | ROCK CORINGS | 20746ED | 104.000 |
104.000 |
$165.000 |
LF | 0.5 |
| 0305 | CONCRETE SEALING | 23378EC | 18,650.000 |
18,650.000 |
$1.870 |
SQFT | 1.0 |
| 0310 | DECK DRAIN | 23813EC | 6.000 |
6.000 |
$850.000 |
EACH | 0.1 |
| 0315 | PPC I-BEAM TYPE HN 42-49 | 23981EC | 720.000 |
720.000 |
$775.000 |
LF | 15.7 |
| 0320 | RAIL SYSTEM SINGLE SLOPE - 40 IN | 25028ED | 486.000 |
486.000 |
$160.000 |
LF | 2.2 |
| 0325 | MOBILIZATION FOR CONCRETE SURF TREATMENT | 26233EC | 1.000 |
1.000 |
$1,250.000 |
LS | 0.0 |
Category Total $2,034,349.61 |
| SM- Project | BR07802892500 | CATEGORY NUMBER | 0004 | CATEGORY Description | DEMOBILIZATION &/OR MOBILIZATION |
| PROJ LN # | Item Description | BID CODE | Bid Qty | Plan Qty | Unit Price | Unit | % of Bid Amt |
| 0330 | MOBILIZATION | 02568 | 1.000 |
1.000 |
$165,000.000 |
LS | 4.6 |
| 0335 | DEMOBILIZATION | 02569 | 1.000 |
1.000 |
$50,349.000 |
LS | 1.4 |
Category Total $215,349.00 |